Vyttila Mobilty Hub Work Progress Report up to 23.03.2011

Published Date:Mar 24, 2011

I. Critical team

Sl No

NCC- Name

Designation

mobile no

1 Sony joseph (AGM)

          9633100042

2 Noel Augustine (Sr.Engineer)

          9995498115

3 Sajesh P P

(AE)

           9995498094

4 Saji Mohanan

(Jr. Engineer)

          9995550380

5 Shinoj P P

( Surveyor )

          9995550165

6 Francis C.P  

(SE QS)

          9995498095


II. Weekly progress report
a) Schedule- PERT Chart


CONSTRUCTION OF MOBILTY HUB AT VYTTILA ,COCHIN
Title Progress Report for the week ending on 15-03-2011
Sl No Name of Activity Scheduled Activity Progress During The Week Delayed / Intime Remark

Date of start

Date of finish

A

FOOD COURT & TOILET BLOCK

 

 

 

 

 

1 Earth work excavation

01.03.2011

14.03.2011

80m3

As per Schedule

 

2 PCC flooring

07.03.2011

25.03.2011

10m3

As per Schedule

 

3 Masonary work

11.03.2011

27.03.2011

40m3

As per Schedule

 

4 Plastering works

01.03.2011

30.03.2011

175m2

As per Schedule

Food court plastering completed Toilet plastering in progress

5 Plumbing & Sanitary work

17.03.2011

30.04.2011

 

As per Schedule

In progress

6 Tile work (Food Court & Toilet block )

18.03.2011

22.04.2011

 

 

 

7 Alum. Work

05.04.2011

27.04.2011

 

As per Schedule

Work in Progress

8 Septic tank – 2 nos

09.03.2011

16.04.2011

 

As per Schedule

Work in Progress

B BUS BAY

 

 

 

 

 

1 Structural steel work & Sheeting work

 

 

 

 

 

a Bay 1-4 ( modification structural steel /sheet laying )

16.03.2011

31.03.2011

 

 

 

b Bay 5-7 ( modification structural steel /sheet laying )

Started

31.03.2011

 

 

 

c Arch erection of balance bays(8-13)

16.03.2011

31.03.2011

 

 

 

d Purlin fabrication & erection Bracing / stiffening & Painting

25.03.2011

25.04.2011

 

 

 

e Kalzip roofing

01.04.2011

10.05.2011

 

 

 

f Bus bay Soffit work

 

 

 

 

Decision awaited

g Flooring

10.04.2011

15.05.2011

 

 

 

C ROAD

 

 

 

 

 

a WBM

 

 

 

 

90% Completed

b Paver

 

 

 

 

 

c Road Connection to Thripunithura road

15.02.2011

10.04.2011

 

 

Earth filling 95% completed, WBM and Paver works remaining



 