I. Critical team |
||||||||||
|
Sl No |
NCC- Name |
Designation |
mobile no |
|||||||
| 1 | Sony joseph | (AGM) |
9633100042 |
|||||||
| 2 | Noel Augustine | (Sr.Engineer) |
9995498115 |
|||||||
| 3 | Sajesh P P |
(AE) |
9995498094 |
|||||||
| 4 | Saji Mohanan |
(Jr. Engineer) |
9995550380 |
|||||||
| 5 | Shinoj P P |
( Surveyor ) |
9995550165 |
|||||||
| 6 | Francis C.P |
(SE QS) |
9995498095 |
|||||||
II. Weekly progress report
a) Schedule- PERT Chart
| CONSTRUCTION OF MOBILTY HUB AT VYTTILA ,COCHIN | ||||||||||
| Title Progress Report for the week ending on 15-03-2011 | ||||||||||
| Sl No | Name of Activity | Scheduled Activity | Progress During The Week | Delayed / Intime | Remark | |||||
|
Date of start |
Date of finish |
|||||||||
|
A |
FOOD COURT & TOILET BLOCK |
|
|
|
|
|
||||
| 1 | Earth work excavation |
01.03.2011 |
14.03.2011 |
80m3 |
As per Schedule |
|
||||
| 2 | PCC flooring |
07.03.2011 |
25.03.2011 |
10m3 |
As per Schedule |
|
||||
| 3 | Masonary work |
11.03.2011 |
27.03.2011 |
40m3 |
As per Schedule |
|
||||
| 4 | Plastering works |
01.03.2011 |
30.03.2011 |
175m2 |
As per Schedule |
Food court plastering completed Toilet plastering in progress |
||||
| 5 | Plumbing & Sanitary work |
17.03.2011 |
30.04.2011 |
|
As per Schedule |
In progress |
||||
| 6 | Tile work (Food Court & Toilet block ) |
18.03.2011 |
22.04.2011 |
|
|
|
||||
| 7 | Alum. Work |
05.04.2011 |
27.04.2011 |
|
As per Schedule |
Work in Progress |
||||
| 8 | Septic tank – 2 nos |
09.03.2011 |
16.04.2011 |
|
As per Schedule |
Work in Progress |
||||
| B | BUS BAY |
|
|
|
|
|
||||
| 1 | Structural steel work & Sheeting work |
|
|
|
|
|
||||
| a | Bay 1-4 ( modification structural steel /sheet laying ) |
16.03.2011 |
31.03.2011 |
|
|
|
||||
| b | Bay 5-7 ( modification structural steel /sheet laying ) |
Started |
31.03.2011 |
|
|
|
||||
| c | Arch erection of balance bays(8-13) |
16.03.2011 |
31.03.2011 |
|
|
|
||||
| d | Purlin fabrication & erection Bracing / stiffening & Painting |
25.03.2011 |
25.04.2011 |
|
|
|
||||
| e | Kalzip roofing |
01.04.2011 |
10.05.2011 |
|
|
|
||||
| f | Bus bay Soffit work |
|
|
|
|
Decision awaited |
||||
| g | Flooring |
10.04.2011 |
15.05.2011 |
|
|
|
||||
| C | ROAD |
|
|
|
|
|
||||
| a | WBM |
|
|
|
|
90% Completed |
||||
| b | Paver |
|
|
|
|
|
||||
| c | Road Connection to Thripunithura road |
15.02.2011 |
10.04.2011 |
|
|
Earth filling 95% completed, WBM and Paver works remaining |
||||