| PROJECT :VYTTILA MOBILITY HUB | 6_12 | 13_19 | 20_26 | 27_02 | 03_09 | 10_16 | 17_23 | 24_30 | Remarks | ||||||
| Weekly shedule | Week | ||||||||||||||
| Construction schedule | 47 days | 01-Mar | 30-Apr | I | II | III | IV | V | VI | VII | VIII | ||||
| Toilet block | Qty | Unit | 47 days | 01-Mar | 30-Apr | ||||||||||
| Earth work excavation | 115.00 | Cum | 10 days | 01-Mar | 14-Mar | 12 | 84 | 31 | completed | ||||||
| Humepipe laying | 32.00 | RM | 3 days | 08-Mar | 10-Mar | 32 | completed | ||||||||
| PCC flooring | 30.00 | Cum | 15 days | 07-Mar | 25-Mar | 2 | 10 | 10 | 10 | completed | |||||
| Masonary works for partion | 125 | Sq.m | 12 days | 11-Mar | 27-Mar | 10 | 0 | 60 | 65 | completed | |||||
| Plumbing pipe laying works | LS | 10 days | 11-Mar | 24-Mar | Work in progress | ||||||||||
| Plastering wall & ceiling | 782.00 | Sq.m | 23 days | 01-Mar | 30-Mar | 34 | 150 | 150 | 150 | 332 | completed. | ||||
| Aluminium works (external Cladding ) | 200 | Sq.m | 12 days | 06-Apr | 20-Apr | 17 | 50 | 100 | 50 | Fabrication work in progress. | |||||
| Flooring ( Tiles ) | 320 | Sq.m | 20 days | 29-Mar | 22-Apr | 16 | 50 | 50 | 100 | 120 | Clading work in progress | ||||
| Structural glazing works | 320 | Sq.m | 18 days | 05-Apr | 27-Apr | 18 | 125 | 125 | 70 | Fabrication work in progress. | |||||
| Electrical Fixtures | LS | 11 days | 01-Apr | 15-Apr | |||||||||||
| Painting | 500 | Sq.m | 14 days | 04-Apr | 20-Apr | 36 | 120 | 240 | 140 | Work in progress | |||||
| Sanitary fittings | LS | 5 days | 26-Apr | 30-Apr | |||||||||||
| Septic tank works | LS | 30 days | 09-Mar | 16-Apr | Completed | ||||||||||
| PROJECT :VYTTILA MOBILITY HUB | 6_13 | 13_20 | 20_27 | 27_03 | 03_10 | 10_17 | 17_24 | 24_31 | Remarks | ||||||
| Weekly shedule | Week | ||||||||||||||
| Construction schedule | 47 days | 01-Mar | 30-Apr | I | II | III | IV | V | VI | VII | VIII | ||||
| Toilet block | Qty | Unit | 47 days | 01-Mar | 30-Apr | ||||||||||
| Earth work excavation | 549.17 | Cum | 10 days | 01-Mar | 14-Mar | 55 | 84 | 31 | completed | ||||||
| Humepipe laying | 593.36 | RM | 3 days | 08-Mar | 10-Mar | -18 | completed | ||||||||
| PCC flooring | 637.54 | Cum | 15 days | 07-Mar | 25-Mar | 43 | -34 | 197 | 198 | completed | |||||
| Masonary works for partion | 681.725 | Sq.m | 12 days | 11-Mar | 27-Mar | 57 | -50 | 244 | 244 | completed | |||||
| Plumbing pipe laying works | 725.909 | LS | 10 days | 11-Mar | 24-Mar | 290 | 290 | Work in progress | |||||||
| Plastering wall & ceiling | 770.09 | Sq.m | 23 days | 01-Mar | 30-Mar | 33 | 150 | 336 | 336 | 332 | completed. | ||||
| Aluminium works (external Cladding ) | 814.279 | Sq.m | 12 days | 06-Apr | 20-Apr | 17 | 152 | 261 | 100 | Fabrication work in progress. | |||||
| Flooring ( Tiles ) | 858.464 | Sq.m | 20 days | 29-Mar | 22-Apr | 16 | 50 | 172 | 297 | 110 | Clading work in progress | ||||
| Structural glazing works | 902.649 | Sq.m | 18 days | 05-Apr | 27-Apr | 18 | 192 | 334 | 120 | Fabrication work in progress. | |||||
| Electrical Fixtures | 946.833 | LS | 11 days | 01-Apr | 15-Apr | 212 | 371 | ||||||||
| Painting | 991.018 | Sq.m | 14 days | 04-Apr | 20-Apr | 36 | 232 | 407 | 140 | Work in progress | |||||
| Sanitary fittings | LS | 5 days | 26-Apr | 30-Apr | |||||||||||
| Septic tank works | LS | 30 days | 09-Mar | 16-Apr | Completed | ||||||||||