Weekly Schedule of the Work which has been Completed

Published Date:Apr 28, 2011

PROJECT :VYTTILA MOBILITY HUB             6_12 13_19 20_26 27_02 03_09 10_16 17_23 24_30 Remarks
Weekly shedule             Week  
Construction schedule      47 days 01-Mar 30-Apr   II III IV V VI VII VIII  
Toilet block  Qty Unit 47 days 01-Mar 30-Apr                    
Earth work excavation 115.00 Cum 10 days 01-Mar 14-Mar 12 84 31             completed
Humepipe laying 32.00 RM 3 days 08-Mar 10-Mar   32               completed
PCC flooring 30.00 Cum 15 days 07-Mar 25-Mar 2 10 10 10           completed
Masonary works for partion 125 Sq.m 12 days 11-Mar 27-Mar 10 0 60 65           completed
Plumbing pipe laying works   LS 10 days 11-Mar 24-Mar                   Work in progress
Plastering wall & ceiling 782.00 Sq.m 23 days 01-Mar 30-Mar 34 150 150 150 332         completed.
Aluminium works (external Cladding ) 200 Sq.m 12 days 06-Apr 20-Apr 17         50 100 50   Fabrication work in progress.
Flooring ( Tiles ) 320 Sq.m 20 days 29-Mar 22-Apr 16       50 50 100 120   Clading work in progress
Structural glazing works 320 Sq.m 18 days 05-Apr 27-Apr 18         125 125 70   Fabrication work in progress.
Electrical Fixtures   LS 11 days 01-Apr 15-Apr                    
Painting 500 Sq.m 14 days 04-Apr 20-Apr 36         120 240 140   Work in progress
Sanitary fittings   LS 5 days 26-Apr 30-Apr                    
Septic tank works   LS 30 days 09-Mar 16-Apr                   Completed
PROJECT :VYTTILA MOBILITY HUB             6_13 13_20 20_27 27_03 03_10 10_17 17_24 24_31 Remarks
Weekly shedule             Week  
Construction schedule      47 days 01-Mar 30-Apr   II III IV V VI VII VIII  
Toilet block  Qty Unit 47 days 01-Mar 30-Apr                    
Earth work excavation 549.17 Cum 10 days 01-Mar 14-Mar 55 84 31             completed
Humepipe laying 593.36 RM 3 days 08-Mar 10-Mar   -18               completed
PCC flooring 637.54 Cum 15 days 07-Mar 25-Mar 43 -34 197 198           completed
Masonary works for partion 681.725 Sq.m 12 days 11-Mar 27-Mar 57 -50 244 244           completed
Plumbing pipe laying works 725.909 LS 10 days 11-Mar 24-Mar     290 290           Work in progress
Plastering wall & ceiling 770.09 Sq.m 23 days 01-Mar 30-Mar 33 150 336 336 332         completed.
Aluminium works (external Cladding ) 814.279 Sq.m 12 days 06-Apr 20-Apr 17         152 261 100   Fabrication work in progress.
Flooring ( Tiles ) 858.464 Sq.m 20 days 29-Mar 22-Apr 16       50 172 297 110   Clading work in progress
Structural glazing works 902.649 Sq.m 18 days 05-Apr 27-Apr 18         192 334 120   Fabrication work in progress.
Electrical Fixtures 946.833 LS 11 days 01-Apr 15-Apr           212 371      
Painting 991.018 Sq.m 14 days 04-Apr 20-Apr 36         232 407 140   Work in progress
Sanitary fittings   LS 5 days 26-Apr 30-Apr                    
Septic tank works   LS 30 days 09-Mar 16-Apr                   Completed



 