| 07.05.2011 | |||||||
| CONSTRUCTION OF MOBILTY HUB AT VYTTILA ,COCHIN | |||||||
| TITLE : PROGRESS REPORT | |||||||
| SL NO | Name of Activity | Scheduled Activity | Progress during the week | Delayed / Intime | Remark | KITCO’s Remark | |
| Date of start | Date of finish | ||||||
| A | FOOD COURT & TOILET BLOCK | ||||||
| 1 | Earth work excavation | 01.03.2011 | 14.03.2011 | As per Schedule | As per Schedule | ||
| 2 | PCC flooring | 07.03.2011 | 25.03.2011 | As per Schedule | As per Schedule | ||
| 3 | Masonary work | 11.03.2011 | 27.03.2011 | As per Schedule | As per Schedule | ||
| 4 | Plastering works | 01.03.2011 | 30.03.2011 | As per Schedule | In completed | ||
| 5 | Plumbing & Sanitary work | 17.03.2011 | 30.04.2011 | In progress | In progress | ||
| 6 | Tile work (Food Court & Toilet block ) | 18.03.2011 | 22.04.2011 | Lapothra flooring 3500 Sqft completed.Vitrified tile flooring 65% Completed. Toilet & corridor tililing dadoing work 70% completed. Balance lapothra granite expected at site within 2 days. | FOOT COURT flooring work are delayed due to the shortage of materials | ||
| 7 | Alum. Work | 05.04.2011 | 27.04.2011 | Work in Progress | In progress | ||
| Septic tank – 2 nose | 09.03.2011 | 16.04.2011 | As per Schedule | Completed | Plastering in progress | ||
| B | BUS BAY | ||||||
| 1 | Structural steel work & Sheeting work | ||||||
| a | Bay 1-4 ( modification structural steel /sheet laying ) | 16.03.2011 | 31.03.2011 | Bus bay 1 to 7 Kalzip top sheet laying 80% completed. Bay 1-4 peripheral Eves drop work completed. | Work in Progress | ||
| b | Bay 5-7 ( modification structural steel /sheet laying ) | Started | 31.03.2011 | Kalzip sheet laying 80% completed in Bay 1 -7. Eves drop work in progress in 5 th Bay. | Work in Progress | ||
| c | Arch erection of balance bays(8-13) | 16.03.2011 | 31.03.2011 | Completed | Arch erection completed from 1st to 13 th bay. | Completed | |
| d | Purlin fabrication & erection Bracing / stiffening & Painting | 25.03.11 | 25.04.11 | Purlin fabrication completed. Purlin erection completed in 1 to 13 th Bay. Bracing work completed except 8&9 bay. Painting in progress from 8 to 13 th bay. | Erection completed.Bracing and painting in progress | ||
| e | Kalzip roofing | 01.04.11 | 10.05.11 | Kalzip sheet laying 80% completed from Bay 1 to 7. | Kalzip sheet laying 80% completed from Bay 1 to 7. Bay 8 to 13 not started | ||
| f | Bus bay Soffit work | 13.04.11 | Kalzip sheet profiling machine moblised at site today. Gutter soffit fabrications details recived today. Work will commence progressively from 1 st bay from 5/5/11 onwards. | Work in Progress | |||
| g | Flooring | 10.04.11 | 15.05.11 | Will commence after soffit works. | |||
| C | ROAD | ||||||
| a | WBM | 90% Completed | |||||
| b | Paver | " | |||||
| c | Road Connection to Thripunithura road | 15.02.2011 | 10.04.2011 | Earth filling completed.WBM work in progress. Additional work of Hume pipe laying in progress. Work was slightly delayed due to delay in clearing of tree roots.Hume pipe laying in progress.Expected to be completed by 05/05/11. | Earth filling in progress.Hume pipe laying completed. | ||