Work Progress Report Till 07-05-2011

Published Date:May 10, 2011

              07.05.2011
CONSTRUCTION OF MOBILTY HUB AT VYTTILA ,COCHIN  
TITLE : PROGRESS REPORT  
SL NO Name of Activity Scheduled Activity Progress during the week Delayed / Intime Remark KITCO’s Remark
Date of start Date of finish
A FOOD COURT & TOILET BLOCK            
1 Earth work excavation 01.03.2011 14.03.2011   As per Schedule   As per Schedule
2 PCC flooring 07.03.2011 25.03.2011   As per Schedule   As per Schedule
3 Masonary work 11.03.2011 27.03.2011   As per Schedule   As per Schedule
4 Plastering works 01.03.2011 30.03.2011   As per Schedule   In completed
5 Plumbing & Sanitary work 17.03.2011 30.04.2011     In progress  In progress
6 Tile work (Food Court & Toilet block ) 18.03.2011 22.04.2011     Lapothra flooring 3500 Sqft completed.Vitrified tile flooring 65% Completed. Toilet & corridor  tililing dadoing work 70% completed. Balance lapothra granite expected at site within 2 days. FOOT COURT flooring work are delayed due to the shortage of materials
7 Alum. Work 05.04.2011 27.04.2011     Work in Progress In progress
  Septic tank – 2 nose 09.03.2011 16.04.2011   As per Schedule Completed Plastering in progress
B BUS BAY            
1 Structural steel work & Sheeting work            
a Bay 1-4 ( modification structural steel /sheet laying ) 16.03.2011 31.03.2011     Bus bay 1 to 7 Kalzip top sheet laying 80% completed.  Bay 1-4 peripheral Eves drop work completed. Work in Progress
b Bay 5-7 ( modification structural steel /sheet laying ) Started 31.03.2011     Kalzip sheet laying 80% completed in Bay 1 -7. Eves drop work in progress in 5 th Bay. Work in Progress
c  Arch erection of balance bays(8-13) 16.03.2011 31.03.2011   Completed Arch erection completed from 1st  to 13 th bay. Completed
d Purlin fabrication & erection Bracing / stiffening & Painting 25.03.11 25.04.11     Purlin fabrication completed.  Purlin erection completed in 1 to 13 th Bay. Bracing work completed except 8&9 bay. Painting in progress from 8 to 13 th bay. Erection completed.Bracing and painting in progress
e Kalzip roofing 01.04.11 10.05.11     Kalzip sheet laying 80% completed from Bay 1 to 7.  Kalzip sheet laying 80% completed from Bay 1 to 7.  Bay 8 to 13 not started
f Bus bay Soffit work   13.04.11       Kalzip sheet profiling machine moblised at site today. Gutter soffit fabrications details recived today. Work will commence progressively from 1 st bay from 5/5/11 onwards. Work in Progress
g Flooring 10.04.11 15.05.11     Will commence after soffit works.  
C ROAD            
a WBM          90% Completed  
b Paver         "  
Road Connection to Thripunithura road 15.02.2011 10.04.2011     Earth filling  completed.WBM work in progress. Additional work of Hume pipe laying in progress. Work was slightly delayed due to delay in clearing of tree roots.Hume pipe laying in progress.Expected to be completed by 05/05/11. Earth filling in progress.Hume pipe laying completed.



 