| 17.05.2011 | ||||||
| CONSTRUCTION OF MOBILTY HUB AT VYTTILA ,COCHIN | ||||||
| TITLE : PROGRESS REPORT | ||||||
| SL NO | Name of Activity | Scheduled Activity | Progress during the week | Delayed / Intime | Remark | |
| Date of start | Date of finish | |||||
| A | FOOD COURT & TOILET BLOCK | |||||
| 1 | Earth work excavation | 01.03.2011 | 14.03.2011 | As per Schedule | Completed | |
| 2 | PCC flooring | 07.03.2011 | 25.03.2011 | As per Schedule | Completed | |
| 3 | Masonary work | 11.03.2011 | 27.03.2011 | As per Schedule | Completed | |
| 4 | Plastering works | 01.03.2011 | 30.03.2011 | As per Schedule | Completed | |
| 5 | Plumbing & Sanitary work | 17.03.2011 | 30.04.2011 | In progress | ||
| 6 | Tile work (Food Court & Toilet block ) | 18.03.2011 | 22.04.2011 | Lapothra flooring 3500 Sqft completed. Vitrified tile flooring 65% Completed. Toilet & corridor tilling dadoing work 80% completed. | ||
| 7 | Alum. Work | 05.04.2011 | 27.04.2011 | Work in Progress.Food Court Elevation Glass fixing 85% completed & Toilet Block 40% completed. | ||
| Septic tank – 2 nos | 09.03.2011 | 16.04.2011 | As per Schedule | Completed | ||
| B | BUS BAY | |||||
| 1 | Structural steel work & Sheeting work | |||||
| a | Bay 1-4 ( modification structural steel /sheet laying ) | 16.03.2011 | 31.03.2011 | Bus bay 1 to 7 Kalzip top sheet laying 80% completed. Bay 1-4 peripheral Eves drop work completed. | ||
| b | Bay 5-7 ( modification structural steel /sheet laying ) | Started | 31.03.2011 | Kalzip sheet laying 80% completed in Bay 1 -7. Bay 1-7 peripheral Eves drop work completed. | ||
| c | Arch erection of balance bays(8-13) | 16.03.2011 | 31.03.2011 | Completed | Arch erection completed from 1st to 13 th bay. | |
| d | Purlin fabrication & erection Bracing / stiffening & Painting | 25.03.11 | 25.04.11 | Purlin fabrication completed. Purlin erection completed in 1 to 13 th Bay. Bracing work completed in all bays. Anticorrosive and blued white Painting work in progress in 8th, 9 th and 10 th bay. | ||
| e | Kalzip roofing | 01.04.11 | 10.05.11 | Kalzip sheet laying 80% completed from Bay 1 to 7. | ||
| f | Bus bay Soffit work | 13.04.11 | Soffit sheet fixing completed from Bay 1 – 5. Soffit fixing work in progress for 6 th bay. | |||
| g | Flooring | 10.04.11 | 15.05.11 | Tiling work completed in 1 st bay. 2nd bay work in progress. | ||
| C | ROAD | |||||
| a | WBM | 90% Completed | ||||
| b | Paver | " | ||||
| c | Road Connection to Thripunithura road | 15.02.2011 | 10.04.2011 | Earth Filling Completed. Laying of Hume pipe Completed. WBM work in progress. | ||