Weekly Work Progress Report Till 24-05-2011

Published Date:May 26, 2011

            17.05.2011
CONSTRUCTION OF MOBILTY HUB AT VYTTILA ,COCHIN
TITLE : PROGRESS REPORT
SL NO Name of Activity Scheduled Activity Progress during the week Delayed / Intime Remark
Date of start Date of finish
A FOOD COURT & TOILET BLOCK          
1 Earth work excavation 01.03.2011 14.03.2011   As per Schedule Completed
2 PCC flooring 07.03.2011 25.03.2011   As per Schedule Completed
3 Masonary work 11.03.2011 27.03.2011   As per Schedule Completed
4 Plastering works 01.03.2011 30.03.2011   As per Schedule Completed
5 Plumbing & Sanitary work 17.03.2011 30.04.2011     In progress 
6 Tile work (Food Court & Toilet block ) 18.03.2011 22.04.2011     Lapothra flooring 3500 Sqft completed. Vitrified tile flooring 65% Completed. Toilet & corridor  tilling dadoing work 80% completed. 
7 Alum. Work 05.04.2011 27.04.2011     Work in Progress.Food Court Elevation Glass fixing 85% completed & Toilet Block 40% completed.
  Septic tank – 2 nos 09.03.2011 16.04.2011   As per Schedule Completed
B BUS BAY          
1 Structural steel work & Sheeting work          
a Bay 1-4 ( modification structural steel /sheet laying ) 16.03.2011 31.03.2011     Bus bay 1 to 7 Kalzip top sheet laying 80% completed.  Bay 1-4 peripheral Eves drop work completed.
b Bay 5-7 ( modification structural steel /sheet laying ) Started 31.03.2011     Kalzip sheet laying 80% completed in Bay 1 -7. Bay 1-7 peripheral Eves drop work completed.
c  Arch erection of balance bays(8-13) 16.03.2011 31.03.2011   Completed Arch erection completed from 1st  to 13 th bay.
d Purlin fabrication & erection Bracing / stiffening & Painting 25.03.11 25.04.11     Purlin fabrication completed.  Purlin erection completed in 1 to 13 th Bay. Bracing work completed in all bays. Anticorrosive and blued white Painting work in progress in 8th, 9 th and 10 th bay.
e Kalzip roofing 01.04.11 10.05.11     Kalzip sheet laying 80% completed from Bay 1 to 7. 
f Bus bay Soffit work   13.04.11       Soffit sheet fixing  completed from Bay 1 – 5. Soffit fixing work in progress for 6 th bay.
g Flooring 10.04.11 15.05.11     Tiling work  completed  in 1 st bay. 2nd bay work in progress.
C ROAD          
a WBM          90% Completed
b Paver         "
Road Connection to Thripunithura road 15.02.2011 10.04.2011     Earth Filling Completed. Laying of Hume pipe Completed. WBM work in progress.



 